1. Name of assignment or project: Preparation of Environment and Social Impact Assessment and Resettlement Action Plan related to the Proposed project of Strengthening of Nzove-Ntora principal transmission pipeline in Kigali City
• Location: Kigali-Rwanda
• Year: 2018
• Source of Funds: Government of Japan
• Client: WASAC Ltd/ KOKUSAI KOGYO CO., Ltd
• Main project features: The proposed project will consist at installation of a new water pipeline with 900mm diameter on a distance of 9.4 km from the Nzove water treatment plant located in Kanyinya sector of Nyarugenge district to Ntora Reservoir located in Gisozi sector of Gasabo district. The installation of such water pipeline requires associated infrastructures such water pump station, access roads, construction of bridges where the pipe crosses river, construction yard for material and construction material.
• Activities performed: Environmental and Social Assessment, preparation of Environment and Social Impact Assessment and Resettlement Action Plan related to the Proposed project
2. Name of assignment or project: Environmental and Social Assessment, review and update of environmental Impact assessment and Resettlement Action plan related to Kigali Bulk Water Supply project
• Year: 2016
• Location: Kigali
• Client: Kigali water Limited/WASAC
• Source of Funds: METITO, MIGA and ADB
• Main project features: The proposed project is a PPP for the construction of water supply infrastructure and provides 40,000m3/day to the Kigali City water supply network.
• Activities performed : Environmental and Social Assessment, review and update of environmental Impact assessment and Resettlement Action plan related to Kigali Bulk Water Supply project
3. Name of assignment or project: Environmental and Social Assessment for Cattle Feedlot, abattoir and meat Processing Plant project in Sudan and Environmental and Social Management System (ESMS) for Elnefeidi Group
• Location: Sudan, Khartoum
• Year: 2018
• Client: Elnefeidi Group
• Source of Funds: African Development Bank
• Main project features: The project consists of three main component including feedlot, abattoir and meet processing plant. To be able to produce yearly target of 175,000 slaughter cattle at a finish weight of 450 kg (57% dressing yield in the slaughter- line), the feedlot operations of Elnefeidi will consist of a feedlot with a standing capacity of 44,800 cattle. For the supply of feeders, two collection centres are planned in concentration areas of livestock. Each collection centre has a standing capacity of circa 600 heads. The capacity of abattoir is planned for 24 hours at 35 cattle per hour and 2 shifts with the holding capacity of 560 cattle (reception area + lairage).
• Activities performed: Environmental and Social Assessment, preparation of Elnefeidi Group Environmental and Social Management System (ESMS) and an Environmental and Social Management Plan (ESMP).
4. Name of assignment or project: Environmental and Social Impact assessment for the Construction of irrigation network and development for 120 ha of Bwanya marshlands(Rujambari-Rufuha)
• Location located in Gicumbi District, Northern Province
• Year: 2018
• Source of Funds: Government of South Korea through COIKA
• Client: Ministry of Agriculture and Animal Resources
• Main project features: The proposed project will consist at rehabilitation of irrigation network and development in Bwanya (Rufuha-Rujambari) marshlands located in Gicumbi district. The marshlands is extend over two districts, namely Gicumbi District of North province in the Sector of Muko and Giti and Gatsibo District of East province in the Muhura and Gasange sectors. Planned works include marshlands development, construction of irrigation canals and night water storages. The potential irrigation area for the Bwanya marshlands is about 120 ha.
• Construction of Main irrigation canals and rehabilitation of marshlands
• Activities performed: Environmental and Social Assessment, preparation of the Environmental and Social Impact Assessment/Environmental and Social Management Plan (ESIA/ESMP)
5. Name of assignment or project: Environmental Impact Assessment related to Exploration and extraction of quarry stones and aggregate manufacturing plant
• Year : 2017
• Location : Jabana, Gasabo, Kigali-Rwanda
• Client : HIMA cement Limited
• Source of Funds: Hima cement Limited
• Main project features: Exploration and extraction of stone quarry crushing plant and aggregate manufacturing plant.
• Activities performed : Environmental and Social Assessment, preparation of Environmental Protection Plan
6. Name of assignment or project : Environmental Impact Assessment Exploration and extraction of minerals in Nemba mining concession
• Year : 2016
• Location : Bugesera district, Rwanda
• Client : Fair Construction Limited
• Main project features : Exploration and extraction of minerals and well as the establishment mini-treatment industry
• Activities performed : Environmental and Social Assessment and Preparation of Environmental Impact Assessment
7. Name of assignment or project: Environmental and Social Audit of Kigali International Airport,
• Year: 2017
• Location: Kigali-Rwanda
• Client: Rwanda Civil Aviation Authority
• Source of Funds: Government of Rwanda
• Main project features: Environmental Audit of all airport facilities and operation including air and noise pollution, waste management, emergency operations, occupational health and safety
• Positions held: Individual Consultant
• Activities performed: Environmental and Social audit, preparation of Environmental audit report and environment action plans
8. Name of assignment or project: Mapping of Environment, Natural resources and climate change Interventions executed under ENR Sector and Related Sector and creation of online portal.
• Year: 2017
• Location: Rwanda, Countrywide
• Client: Ministry of Natural Resources
• Main project features: Mapping all interventions in land management, Water resources, forestry. Mining and climate change and creation of online portal for information sharing
• Positions held: Individual Consultant
• Activities performed: Coordinate all exercised and lead the preparation of detailed report of all interventions and training of Ministry staffs.
9. Name of assignment or project: Development of National Climate change mainstreaming strategy for Rwanda.
• Location: Kigali-Rwanda
• Year: 2018
• Client: United Nations Development Program/UNDP
• Main project features: Review of national strategic plans, identification and documentations of mainstreaming strategy and Preparation of draft mainstreaming strategy
• Positions held: National consultant
• Activities performed: Consultation, data Collection and report preparation and presentation
10. Name of assignment or project: Rwanda Sustainable Water and Sanitation Program, additional financing.
• Location: Rwanda-Countrywide
• Year : 2018
• Source of Funds: African Development Bank(AfDB)
• Client: Water and Sanitation Corporation(WASAC)/African Development Bank(ADB)
• Main project features: The additional financing, is structured under three Components namely: (i) Water Supply Infrastructure and Services Improvement component, (ii) sanitation infrastructure and services improvement and (iii) Institutional Support. Water Supply infrastructure and service improvement is the major program and will consist at providing water supply infrastructure including water treatment Plant (WTP), Water reservoirs, and water intake and water pipelines.
• Positions held: Individual Consultant
• Activities performed: Environmental and Social Assessment, preparation of Environmental and Social Management Framework(ESMF) and Environmental and Social Impact assessment(ESIA) for 8 subprojects
11. Name of assignment or project : Environmental and Social Assessment, Preparation of Environmental Impact Assessment, Occupational Health and Safety Plan and Resettlement Action Plan Electrification Project in Western Zone of Rwanda
• Year : 2016
• Location : Western zone of Rwanda
• Source of Funds
• Client : Overseas Infrastructure Alliance/ EARP-EDCL
• Main project features : ESMP, RAP and ESH related to the electrification in Western zone of Rwanda
• Activities performed : Environmental and Social Assessment, Preparation of Environmental Impact Assessment, Occupational Health and Safety Plan and Resettlement Action Plan including Baseline studies
12. Name of assignment or project : Environmental and Social Assessment ,Preparation of Environmental management Plan, Resettlement Action Plan Rehabilitation of irrigation facilities in Rwamagana District,
• Year : 2016
• Location : Rwamagana District
• Client : Japanese International Cooperation Agency(JICA)
• Main project features : Environmental impact Assessment , Resettlement Action Plan and Socio-economic baseline studies related to the irrigation projects in Rwamagana District
• Activities performed : Environmental and Social Assessment ,Preparation of Environmental management Plan, Resettlement Action Plan and Occupational Health and safety Plan for
13. Name of assignment or project : Preparation of Environmental Impact Assessment for Mineral exploration Cassiterite, Coltan in Rwaromba perimeter
• Year : 2015
• Location : Ngoma District
• Client : Agashami Mining Limited
• Main project features : Extraction of Cassiterite and Coltan
• Activities performed : Environmental management Plan and abbreviated Resettlement Action Plan
14. Name of assignment or project : Environment and Social Impact Assessment for Kigali Bulk Water Supply project
• Year : 2015
• Location : Kigali
• Client : Kigali-Water project LTD and WASAC
• Main project features: The proposed scheme is designed to be a 40,000m3/day groundwater scheme, extracting groundwater from the south bank of the Nyabarongo River and then supplying the water north to Kigali. This scheme comprises a wellfield, WTP and associated forwarding infrastructure to convey the water to new storage reservoirs
• Activities performed : Environmental and Social Assessment, Preparation of environmental Impact assessment and Resettlement Action plan
15. Name of assignment or project : Preparation of Environmental Impact Assessment for Mineral exploration Cassiterite, Coltan in MWESA perimeter
• Year : 2015
• Location : Mwesa perimeter is located in Murama cell, Nyamata sector in Bugesera district, Eastern Province
• Client : Agashami Mining Ltd
• Main project features : Extraction of Cassiterite and Coltan
• Activities performed : Environmental and Social Assessment, Preparation of Environmental management Plan and Abbreviated Resettlement Action plan
16. Name of assignment or project : Environmental and social studies for the Planned marshlands development in Rusuli
• Year : 2015
• Location : Huye district, Rwanda
• Client : WELT HUNGER HILFE (WHH)also known as “Agro-Action Allemande
• Main project features: The project aim at developing 120 ha with irrigation and drainage infrastructure as well as the protection of the sub-catchments. The proposed projects will use the community-led and eco-friendly approach to ensure the balance of socio-economic and ecological functions of marshlands.
• Activities performed : Environmental and Social Assessment, Preparation of Environmental Impact assessment and Resettlement Action plan
17. Name of assignment or project : Environmental and Social Impact assessment for Sand removal and exploitation project at Ruhango watercourse
• Year : 2015
• Location : Rwanda
• Client : Mr. SIMPARISHEMA Michel & Mr. HAKIZIMANA J.Baptiste
• Main project features :
• Activities performed : Preparation of Environmental Impact Assessment (EIA) and socio-economic baseline studies